May a professional stop working when the client unreasonably denies the work already performed?
In the case discussed, the engineer's right to demand the next payment was not yet clear: the contract linked payment to milestones and did not provide for early payment when the project was delayed. Since money is difficult to recover under an unclear contract, the client might have prevailed on the payment's timing. Nevertheless, the beit din considered the engineer justified in quitting because the client claimed that practically nothing had been done, a claim the court verified was unreasonable. This gave substantial reason to expect resistance to justified payment demands in the future.
A practical halachic question: the final ruling is for your rabbi.
Quote from the source«Had the project not been frozen, pl admits that it was too early for further payment.»